我正在尝试实施一条特定的资源曲线,计算仅在工作日(星期一至星期五)的两个指定日期的预算工作时间的分布。这已在Primavera P6中完成,但正在寻找python解决方案。
以图表形式显示的多种资源的示例:Multiple Resource Graph
这些曲线基于:Resource Curve
import pandas as pd
df = pd.DataFrame({'Activity ID':['XXXX-XXXX','XXXX-XXXX','XXXX-XXXX','XXXX-XXXX','XXXX-XXXX'],
'Resource':['Mechanical', 'Electrical ', 'Pipelines ', 'Process ', 'Project Management'],
'Start':['2019-01-16' , '2019-01-17', '2019-01-18', '2019-01-21', '2019-02-17'],
'Finish':['2019-10-02', '2019-09-05', '2019-10-02', '2019-07-18', '2019-07-26'],
'Current Date':['2019-05-05', '2019-05-05', '2019-05-05', '2019-05-05', '2019-05-05'],
'Budgeted Labor Units':[20, 300, 400, 200, 150],
'Remaining Labor Units:':[10, 100, 200, 50, 30]})
print(df)
Activity ID Resource Start Finish Current Date \
0 XXXX-XXXX Mechanical 2019-01-16 2019-10-02 2019-05-05
1 XXXX-XXXX Electrical 2019-01-17 2019-09-05 2019-05-05
2 XXXX-XXXX Pipelines 2019-01-18 2019-10-02 2019-05-05
3 XXXX-XXXX Process 2019-01-21 2019-07-18 2019-05-05
4 XXXX-XXXX Project Management 2019-02-17 2019-07-26 2019-05-05
Budgeted Labor Units Remaining Labor Units:
0 20 10
1 300 100
2 400 200
3 200 50
4 150 30
目标是输入开始日期和结束日期,计算两者之间的工作日,然后根据资源曲线分配这些天的预算工作时间。 Resource Curve
将对所有资源执行此操作,然后通过matplotlib绘制图表以显示项目资源需求。
下一步是设置当前日期,并用剩余的劳动单位重新计算剩余的分配日期。 Progressing resources
我是python的新手,因此非常感谢您的帮助和建议。
谢谢