我正在努力解决问题,要求在1990年+ N-1年的每个工作日发现第13天发生了多少次。
int weekDay = 1;
int week[] = {0,0,0,0,0,0,0};
N = 20;
for (int year = 1990; year <= 1990+N-1; year++){
for (int month = 1; month <= 12; month++){
int days = numberOfDays(year,month);
for (int day = 1; day <= days; day++){
if (day == 13)
week[weekDay] += 1;
weekDay += 1;
if (weekDay > 7)
weekDay = 1;
}
}
}
这是我的解决方案,但是我在一年中陷入无限循环,似乎无法修复它。
编辑:numberOfDays函数。
int numberOfDays(int year, int month)
{
if (month == 2 && leapYear(year))
return 29;
else if (month == 2)
return 28;
if (month == 9 || month == 4 || month == 6 || month == 11)
return 30;
return 31;
}
答案 0 :(得分:5)
您正在使用1..7范围内的工作日,但直方图数组week[]
的索引编号为0..6。
一种可能的解决方案 - 改变:
week[weekDay] += 1;
为:
week[weekDay - 1] += 1;
另一个解决方案 - 让week[]
个元素变大,不要使用元素0,即更改:
int week[] = {0,0,0,0,0,0,0};
为:
int week[] = {0,0,0,0,0,0,0,0};
第三种可能的解决方案 - 使用0..6范围内的工作日,即更改:
int weekDay = 1;
为:
int weekDay = 0;
并改变:
if (weekDay > 7)
weekDay = 1;
为:
if (weekDay > 6)
weekDay = 0;
答案 1 :(得分:0)
关接一个。您的week[]
数组有7个元素,索引为0..6。您写入week[7]
,它会覆盖您不想要的内容,例如year
变量。