我的项目时间表如下。我需要从开球会议开始从1号开始。直到启动,我使用了定制的wbs代码,即M1,M2,M3,M4。这是工作。从关于病房的启动会议开始,我需要开始1 1.1 1.2,2,2.1,2.2等
现有时间表
WBS Task name
1 M1: Milestone1
2 M2: Milestone2
3 M3: Milestone3
4 M4: Milestone4
5 Kick-off meeting
6 Requirement
6.1. Requirement collection
6.2. Requirement priority
6.3. Finalise requirements
7 Design
7.1 High level design
7.2 Low level design
8 Implementation
8.1 coding
8.2 code review
9 Testing
9.1 Test plan
9.2 Test case preparation
9.3 Start Testing
10 Delivery
10.1 Deliver to customer
10.2 Release resource
我需要使用wbs代码更改上面的WBS,如下所示。
预计时间表
WBS Task name
M1: Milestone1
M2: Milestone2
M3: Milestone3
M4: Milestone4
1 Kick-off meeting
2 Requirement
2.1. Requirement collection
2.2. Requirement priority
2.3. Finalise requirements
3 Design
3.1 High level design
3.2 Low level design
4 Implementation
4.1 coding
4.2 code review
5 Testing
5.1 Test plan
5.2 Test case preparation
5.3 Start Testing
6 Delivery
6.1 Deliver to customer
6.2 Release resource
我尝试使用Project - > wbS - >定义代码和重新编号,但两者都不起作用。
答案 0 :(得分:1)
使用自定义大纲代码,而不是内置WBS字段。然后你可以任何你想要的方式。将自定义代码命名为CWBS或PWBS或类似名称,以便区分它们。