排除2个日期之间的假期

时间:2017-06-13 08:27:41

标签: javascript html

我在互联网上搜索过,最后我把这段代码放进去了 Weekend Exclusion

OR

function calcBusinessDays(dDate1, dDate2) { // input given as Date objects
    var iWeeks, iDateDiff, iAdjust = 0;
    if (dDate2 < dDate1) return -1; // error code if dates transposed
    var iWeekday1 = dDate1.getDay(); // day of week
    var iWeekday2 = dDate2.getDay();
    iWeekday1 = (iWeekday1 == 0) ? 7 : iWeekday1; // change Sunday from 0 to 7
    iWeekday2 = (iWeekday2 == 0) ? 7 : iWeekday2;
    if ((iWeekday1 > 5) && (iWeekday2 > 5)) iAdjust = 1; // adjustment if both days on weekend
    iWeekday1 = (iWeekday1 > 5) ? 5 : iWeekday1; // only count weekdays
    iWeekday2 = (iWeekday2 > 5) ? 5 : iWeekday2;

    // calculate differnece in weeks (1000mS * 60sec * 60min * 24hrs * 7 days = 604800000)
    iWeeks = Math.floor((dDate2.getTime() - dDate1.getTime()) / 604800000)

    if (iWeekday1 <= iWeekday2) {
      iDateDiff = (iWeeks * 5) + (iWeekday2 - iWeekday1)
    } else {
      iDateDiff = ((iWeeks + 1) * 5) - (iWeekday1 - iWeekday2)
    }

    iDateDiff -= iAdjust // take into account both days on weekend

    return (iDateDiff + 1); // add 1 because dates are inclusive
  }

我不知道如何添加代码来排除假期。我知道我必须创建一个数组来存储假期,但之后我就陷入了困境。我需要你的帮助,非常感谢。

1 个答案:

答案 0 :(得分:0)

只需遍历假期数组并检查日期是否在范围内,并检查假期是在星期六或星期日,在这种情况下它已被计算。以下是修改后的示例。

function calcBusinessDays(dDate1, dDate2, holidays) { // input given as Date objects
    var iWeeks, iDateDiff, iAdjust = 0, i;
    if (dDate2 < dDate1) return -1; // error code if dates transposed
    var iWeekday1 = dDate1.getDay(); // day of week
    var iWeekday2 = dDate2.getDay();
    iWeekday1 = (iWeekday1 == 0) ? 7 : iWeekday1; // change Sunday from 0 to 7
    iWeekday2 = (iWeekday2 == 0) ? 7 : iWeekday2;
    if ((iWeekday1 > 5) && (iWeekday2 > 5)) iAdjust = 1; // adjustment if both days on weekend
    iWeekday1 = (iWeekday1 > 5) ? 5 : iWeekday1; // only count weekdays
    iWeekday2 = (iWeekday2 > 5) ? 5 : iWeekday2;

    // calculate differnece in weeks (1000mS * 60sec * 60min * 24hrs * 7 days = 604800000)
    iWeeks = Math.floor((dDate2.getTime() - dDate1.getTime()) / 604800000)

    if (iWeekday1 <= iWeekday2) {
      iDateDiff = (iWeeks * 5) + (iWeekday2 - iWeekday1)
    } else {
      iDateDiff = ((iWeeks + 1) * 5) - (iWeekday1 - iWeekday2)
    }

    iDateDiff -= iAdjust; // take into account both days on weekend

    for(i = 0; i < holidays.length; i++) {
      if(holidays[i] >= dDate1 && holidays[i] <= dDate2 && holidays[i].getDay() != 0 && holidays[i].getDay() != 6) {
        iDateDiff--;
      }
    }

    return (iDateDiff + 1); // add 1 because dates are inclusive
  }

var holidays = [ new Date(2017, 5, 2), new Date(2017, 5, 3), new Date(2017, 5, 4), new Date(2017, 5, 5) ];

calcBusinessDays(new Date(2017,1,1), new Date(), holidays);
// returns 93