我试图在特定天数后找到日期。 我的查询如下:
UPDATE [PST].[dbo].[tbl_Project_tracker1]
SET Predicted_Eng_Comp_date = tb2.Predicted_Eng_Comp_date
FROM (SELECT NETWORK_NO,
dateadd(DAY, 20, Actual_Eng_Start_date) as Predicted_Eng_Comp_date
FROM [PST].[dbo].[tbl_Project_tracker1]
) as tb2
WHERE [NETWORK_NO] = tb2.[NETWORK_NO]
查询工作正常,但我正在寻找工作日。我该如何计算?
答案 0 :(得分:0)
请使用下面的查询(替换您当前的查询):
UPDATE [PST].[dbo].[tbl_Project_tracker1] SET Predicted_Eng_Comp_date = DATEADD(DAY, 20, Actual_Eng_Start_date)