Project 2013每日需求摘要

时间:2016-08-17 16:48:34

标签: project

我正在试图弄清楚如何显示我们建筑项目的日常需求,这些项目规模庞大,不可能分配个别资源。

所以这就是我所拥有的,自定义数字列是一个显示工作\持续时间的公式,它告诉我在计划的持续时间内完成该任务所需的工人数量。

现在我要做的是提供一份报告,该报告向我提供当天所需工人的每日摘要或本周的平均值。

我有什么想法可以做到这一点?

1 个答案:

答案 0 :(得分:0)

如果您愿意,请查看您的日常需求,您只需更改视图即可。

https://support.office.com/en-us/article/Change-the-timescale-in-a-view-3c81c793-a5fd-4339-bb10-3c9960b8c55f

"On the View menu, select a view that uses a timescale, such as the Gant
  Chart, Task Usage, or Resource Graph view.

 On the Format menu, click Timescale, and then click the Top Tier, Middle
 Tier, or Bottom Tier tab.

 In the Show list, select the number of tiers that you want to display 
 in the timescale. By default, two tiers are displayed.

 On the tab for the displayed timescale tier, in the Units box, select
  the time unit that you want to use. The types of units range from years to  
 minutes.

 In the Label list, select the label format that you want to use to 
 display the time unit.

 In the Count box, type or select a number to specify the frequency 
 of unit labels on the timescale tier."

例如,如果单位为周,而您键入2,则时间刻度图层将分为2周段。“