我需要生成两个给定日期之间的所有日期。只要只有一个日期范围,这样就可以正常工作。但是,如果我有多个日期范围,则此解决方案不起作用。我在这里以及在asktom上搜索过,但找不到相关的指针/解决方案。
我使用all_objects和CONNECT BY ROWNUM尝试了两种解决方案,但没有运气。以下是问题陈述:sqlfiddle
输入
ID START_DATE END_DATE
101 April, 01 2013 April, 10 2013
102 May, 10 2013 May, 12 2013
输出
ID Dates
101 April, 01 2013
101 April, 02 2013
101 April, 03 2013
101 April, 04 2013
101 April, 05 2013
101 April, 06 2013
101 April, 07 2013
101 April, 08 2013
101 April, 09 2013
101 April, 10 2013
102 May, 10 2013
102 May, 11 2013
102 May, 12 2013
答案 0 :(得分:6)
select
A.ID,
A.START_DATE+delta dt
from
t_dates A,
(
select level-1 as delta
from dual
connect by level-1 <= (
select max(end_date - start_date) from t_dates
)
)
where A.START_DATE+delta <= A.end_date
order by 1, 2
答案 1 :(得分:3)
请尝试:
select
distinct ID,
START_DATE+level-1 DATES
from dual a, TABLE_DATES b
connect by level <= (END_DATE-START_DATE)+1
order by ID;
答案 2 :(得分:1)
select g.cycle_dt
from
(select to_date(d,'DD-MM-YYYY') cycle_dt
from dual
model
dimension by (trunc(to_date('30092015', 'DDMMYYYY')) d)
measures (0 y)
rules (
y[for d from trunc(to_date('30092015', 'DDMMYYYY')) to to_date('30102015', 'DDMMYYYY') increment 1]=0
)) g
order by g.cycle_dt;
答案 3 :(得分:0)
WITH NUMS AS (
SELECT LEVEL-1 DaysToAdd
FROM DUAL
CONNECT BY LEVEL <= (
SELECT MAX(END_DATE - START_DATE + 1)
FROM HOLIDAY)
)
SELECT START_DATE + DaysToAdd DATE_TIME, DESCRIPTION, IS_SCHOOL_HOLIDAY, UPDATE_BY, CREATE_DATE
FROM HOLIDAY
CROSS JOIN NUMS
WHERE HOLIDAY.END_DATE - HOLIDAY.START_DATE > DaysToAdd
ORDER BY 1, 2;