项目有多个任务,其中有多个任务
项目(1-n) - >任务(1-n) - >分配
“任务”表中的字段是“计划时间”。
“作业”表上的字段为“已指定时间”。
如何在单个查询中获取所有项目的计划时数和分配时间?
答案 0 :(得分:6)
编辑:此答案提供的结果不正确,但我会将其保留用于历史目的。
我认为这会帮助你。我无法弄清楚如何摆脱Distinct
。
Select Distinct
Project.ProjectId,
Sum(Task.PlannedHours)
Over (Partition By Project.ProjectId) As PlannedHours,
Sum(Assignment.AssignedHours)
Over (Partition By Project.ProjectId) As AssignedHours
From Project
Inner Join Task On Project.ProjectId = Task.ProjectId
Inner Join Assignment On Task.TaskId= Assignment.AssignmentId
这是我的测试脚本。
Declare @Project Table (ProjectId Int)
Declare @Task Table (TaskId Int, ProjectId Int, PlannedHours Int)
Declare @Assignment Table (AssignmentId Int, TaskId Int, AssignedHours Int)
Insert Into @Project (ProjectId) values (1)
Insert Into @Project (ProjectId) values (2)
Insert Into @Project (ProjectId) values (3)
Insert Into @Task (TaskId, ProjectId, PlannedHours) values (1, 1, 10)
Insert Into @Task (TaskId, ProjectId, PlannedHours) values (2, 1, 10)
Insert Into @Task (TaskId, ProjectId, PlannedHours) values (3, 2, 11)
Insert Into @Task (TaskId, ProjectId, PlannedHours) values (4, 3, 12)
Insert Into @Assignment (AssignmentId, TaskId, AssignedHours) values (1, 1, 2)
Insert Into @Assignment (AssignmentId, TaskId, AssignedHours) values (2, 1, 2)
Insert Into @Assignment (AssignmentId, TaskId, AssignedHours) values (3, 2, 2)
Insert Into @Assignment (AssignmentId, TaskId, AssignedHours) values (4, 3, 3)
Select Distinct
Project.ProjectId,
Sum(Task.PlannedHours)
Over (Partition By Project.ProjectId) As PlannedHours,
Sum(Assignment.AssignedHours)
Over (Partition By Project.ProjectId) As AssignedHours
From @Project Project
Inner Join @Task Task On Project.ProjectId = Task.ProjectId
Inner Join @Assignment Assignment On Task.TaskId= Assignment.AssignmentId
答案 1 :(得分:5)
select p.ProjectID, t.PlannedHoursSum, a.AssignedHoursSum
from Projects p
inner join (
select ProjectID, sum(PlannedHours) as PlannedHoursSum
from Tasks
group by ProjectID
) t on p.ProjectID = t.ProjectID
inner join (
select t.ProjectID, sum(AssignedHours) as AssignedHoursSum
from Tasks t
inner join Assignments a on t.TaskID = a.TaskID
group by t.ProjectID
) a on p.ProjectID = a.ProjectID